In 2025 Leitner-Poma and Alta relocated the Supreme lift to follow a straight alignment rather than the previous bend path.The bottom terminal sits in the same location as before but shifted angle slightly.Both terminal foundations were able to be re-used.View riding up with the old path to the right.The top terminal also stayed in the same spot but shifted angle slightly.Side view of the return station.The new line features one extra tower and the same number of carriers.Lower lift line at tower 10.View up the steep part of the line.Towers 1 and 2.View back down with the old path clearly visible.View riding up the line.Middle section of the line.Tall tower 13.Every tower foundation had to be re-poured and four towers were sent down to Skytrac to be modified.Upper station under cover.Angled tower.New tower 12.T11.View up Supreme Challenge.Lift overview.