5 thoughts on “Wizard – Mt. Rose, NV

  1. Dan Bryant's avatar Danny Bryant August 25, 2022 / 1:13 pm

    The webcam today seems to show Wizard getting a load test (there were cardboard boxes with plastic bag inserted in the boxes on the chairs). To the lift mechanics out there, would this occur on a existing lift if the rope was spliced or replaced, or could it be for another reason?

    Like

    • Michael's avatar Michael August 25, 2022 / 1:44 pm

      A rope replacement or re-splice would not require a load test. A modification to the drive or a capacity increase would. Without know the maintenance sequence, it’s possible they are doing their Periodic (7 year) Dynamic Test which is required by ANSI.

      Liked by 1 person

      • Dan Bryant's avatar Danny Bryant August 25, 2022 / 8:05 pm

        That makes perfect sense since in 2015, Pondo was moved to a new alignment and renamed Wizard. Thanks for the clarification as always.

        Liked by 1 person

        • Kirk's avatar Kirk August 25, 2022 / 8:30 pm

          The lift was load tested (acceptance test) because the lift got a new Drive and control system.

          Liked by 2 people

  2. FlyballSkiLifts's avatar FlyballSkiLifts May 12, 2024 / 7:57 am

    I’ve never seen that motor room enclosure before. Are there any other lifts that have it?

    Like